1.0
Setting up the Dual-Column CCN (CCN-200)
Several steps are required for initial CCN-200 set-up:
•
Unpacking and mounting the instrument
•
Connecting CCN components such as the power cables, supply and drain bottles, and touch
screen monitor
•
Setting the flow and humidifying the instrument (humidification can take up to 12 hours and
must be performed every time the CCN is dry when started)
•
Checking that the CCN is functioning properly
The following sections describe these steps in detail.
Any time the CCN is shipped, it must be dried out and properly repacked prior to shipment. Failing to
follow proper procedure will result in damage to the instrument. See section 10.0 for details on
drying out and packing the instrument.
1.1
Unpacking
To minimize the potential for damage in shipping, the Dual Column CCN arrives on a 36” x 36” pallet
with a fitted case, special frame and protective hood (Figure 1). The frame can be substituted as a
bench stand for the unit.
Figure 1: Dual CCN with Shipping Hood, Pallet and Fitted Case