4.3.4. Clamps for connecting powering transformer S1, S2 (21-24, fig.2)

Clamps are used to connect built-in powering transformer.

4.3.5. Connector for engine encoder EN CODER (13, fig.1)

Connector is used to connect built-in encoder in SWIFT6 drive engine.

4.3.6. Clamps for connecting signal lamp Lam (3-4, fig.2)

Clamps are used to connect optical signaling of engine operation (LAM. and common clamp). Use 230V, 

max. 5A lamps.

Clamps for connecting signal lamp LC (5-4, fig.2)

Clamps are used to connect illumination (L.C. and common clamp). Output switches on during the start 

of the engine and is active for 3 min. after total closing of the gate. Use lamps for 230 V,max.5A voltage.

4.3.9. Programmable output spia clamp (15, fig.2)

Depending  on  the  DIP-SWITCH  configuration,  tab.1,  this  output  can  serve  one  of  the  following 

functions:

powering transmitters of photocells - for photo-test function, the system must have two lines of powering 
photocells. First connected to clamps 13 and 14 which power the receiver, and second for clamps 15 and 14, 
powering transmitters (DIP-SWITCH 7 set ON). The driver checks the efficiency of photocells by controlling 
the reaction of the photocell receiver to the disappearance of the infrared light beam at every start of the 
gate movement. If everything is correct the engine is started. The error of the test blocks the move in case of 
detecting the breakdown what is signaled by the switchboard with the signal lamp. Photo test also works for 
the possible second pair of photocells (JOL input). 

Photo test function significantly increases the security 

level. Activating photo test function – see tab.1.

signaling opened gate – it is possible to connect outside signaling lights which will signal the phase in which 

the  gate  currently  is  by  giving  flashes  in  different  frequency:  slow  flickering  -  opening,  fast  flickering  - 
closing, 2 flashes - countdown of closing time (see fig. 2). Output load is 100 m A what is sufficient for 
controlling electromagnetic transmitters 24 VAC.

4.3.10. Clamps for connecting photocells FT1 (11, fig.2)

FOTO1 input (FT1) is dedicated to the photocell of the gate having the function of stopping the gate 

move while closing. Correctly configured JOLLY input (JOL) can perform the function of stopping the gate during 
closing and opening, according to tab. 1. Photocell input must be closed for the clamp C (common clamp of 
inputs) in the configuration of NC contacts.

It is possible to connect to clamp PA the momentary switch NO type, which, depending on settings, will 

activate OPENING.

It is possible to connect to clamp PC the momentary switch NO type, which will activate CLOSING.
It  is  possible  to  connect  to  the  clamp  P/P  the  momentary  switch  NO  type,  which  will  control  the 

automation according to the set operation mode (see tab. 1).

Connect the momentary  switch (monostable) type NC to the clamp STOP (STP).  
All unused inputs NO type should be left  not connected, but NC type  inputs should be closed with the 

clamp C. Activating of the manual control switch is by its momentary pressing.

4.3.12. Clamp of programmable input JOL (10, fig.2)

It is possible to connect to the JOLLY clamp (JOL), after its correct configuration (see tab.1) the 

following:

- safety edges – function of emergency stop

NC input – after breaching this input the driver reverses the direction of movement of the gate for a few 
seconds.

- time driver – timer function

Connecting 

the clock with contact output allows for automatic opening and closing of the gate in specified time periods. 

4.3.7. 

4.3.8. Clamps for powering accessories 24Vac (13-14, fig.2)

The driver has accessories powering outputs 24VAC of maximum load 1A. Remember that ampacity of 

24Vac output and output of photocells transmitters powering (spia) is 1A together.

4

4

4.3.11.Clamps for manual control PA, PC, P/P, STP (6-9, fig.2)

6

Summary of Contents for SWIFT6

Page 1: ...AUTOMATION SYSTEMS DRIVER FOR SWIFT6 DRIVE Assembly manual for the installers SWIFT6 CB ver 1 0 automation systems ...

Page 2: ......

Page 3: ...ards associated with movingofmovablemechanicalelementssuchascrushing hitchingordetachment DTM System company is not responsible for safe and efficient operation of the device in case of applyingcomponentsnotbeing productsofferedbyDTMSystem Useonlyoriginalpartswhileservicing Donotalterorchangetheelementsofthedevice Inform the end user of the manner of the service dealing with breakdown and about th...

Page 4: ...ver ensures correct and safe operation only when installed and used according to the given safety rules DTM System is not responsible for accidents resulting from incorrect usage or non professional installation of thedevices Please make sure that the persons installing maintaining or operating gate automation follow theseinstructions Itisnecessarytokeeptheseinstructionsinsuchaplacethattheyareeasy...

Page 5: ...ressureedgesanditalsohasencodersystemefficientlydetectingtheoverloadingcausedby the unintentional resistances in the move of the gate The driver detects and also uses the operation of internal magnetic limit switches of the motor Moreover the driver enables the adjustment of the power and has a functionofslowingdownduringstartandstop Thedriverhasaradioreceiverconnector 3 Technicaldata Basic parame...

Page 6: ...eters to the current installation inparticularitisnecessaryto 4 alwayssetthepowerofmotors 4 alwayssetopeningandclosingtimesandthelimitofoverloadingsafetybarrier Scrupulously follow designed connections If uncertain do not try but read relevant detailed technical cardsofinstalleddevices Incorrectconnectionscancauseseriousdamageinthedriverandotherdevices 1 Connector powering the transformer 2 Transf...

Page 7: ...ust be connected to clamps IfwhileprogrammingthegateopensinthewrongwayitisnecessarytochangewiresonclampsCH andAP 4 3 3 ClampsforconnectinglimitswitchFCA C FCC 18 20 fig 2 Clamps are used to connect built in limit switch Magnets which cooperate with the switch have different polarization Before the programming make manual move with gate and make sure that the switch correctlyinterpretsoutermostposi...

Page 8: ...g opening fast flickering closing 2 flashes countdown of closing time see fig 2 Output load is 100 m A what is sufficient for controllingelectromagnetictransmitters24VAC 4 3 10 ClampsforconnectingphotocellsFT1 11 fig 2 FOTO1 input FT1 is dedicated to the photocell of the gate having the function of stopping the gate movewhileclosing CorrectlyconfiguredJOLLYinput JOL canperformthefunctionofstopping...

Page 9: ...8 29 30 31 F0 3A 24V motor Rx Tx control board supply 24VAC orange Signal lamp 230VAC Lamp 230VAC OPEN PROG STOP P P CLOSE STEP BY STEP STOP JOLLY PHOTO1 COM photocells with photo test power supply COM MOTOR blue PE ENCODER Transformer power output Control board supply 12VAC white Limit switch supply 24V yellow COM brown FC 1 green FC 2 white CAPACITOR FCC Ap Ch P P Stop Jolly FT1 FCA Supply 230V ...

Page 10: ...themiddleoftheway 1 fig 3 4 press PROG STOP button and hold it pressed for about 3 seconds until L1 diode does not light constantly 2 fig 3 Driverisintheprogrammingmode 4 Press P P button The gate will start moving in direction toward closing 3 fig 3 If the gate moves on the direction towards opening it is necessary to change the direction of engine operation and limit switch operation seept 4 3 2...

Page 11: ...Ifthisopeningrequiresmodification actinthefollowingwayusingJOLLYinput clamp10fig 2 4 With the gate closed enter the programming mode by holding the PROG STOP button up to the moment untilaL1diodeturnson 4 PressPEDbutton thegatestartsopening 4 Next press PED button at the moment when the gate reaches the demanding position of opening for pedestrians 4 Thegatestops nextitstartsclosing Thedrivesgoeso...

Page 12: ...f slowing down standard slowing down increased slowingdownforheavierautomation Procedureofslowingdowntypechange 4 disconnectthedriverpowersupply 4 connectthepowersupplyagainholdingpressedSTOP PROGbuttons 4 L1diodeturnsonafter3seconds 4 still holdingSTOP PROG buttons set DIP SWITCH 9 from theOFF position to theON if DIP SWITCH is set ON switchitontheOFFpositionandnextON 4 L1diodestartspulsing 4 fas...

Page 13: ...CAUTION SETTINGS CHANGE REQUIRE DRIVE RESTART BY SWITCHING MOTOR SUPPLY OFF FORAMOMENTORBYSHORTCIRCUITOFRESETPINS 15 fig 1 open stop close open close While opening after pressing P P button the gate stops for a few seconds later it closes While closing after pressing P P button the gate stops for a few seconds later it opens always opens While closing pressing P P button stops the gate for a few s...

Page 14: ...n themotorshouldmakeamovetowardsclosing 4 Sprawdziæ funkcjê ZAMYKANIE u ywaj c przycisku pilota lub przycisku rêcznego PC Przy ca kowicie lub czêœciowo otwartej bramie podaæ impuls z przycisku ZAMYKANIE si ownik powinien wykonaæ ruch w kierunkuzamykania 4 Check STOP function by using manual button During motor move in direction towards closing or opening giveimpulsefromSTOPbutton thedriveshouldsto...

Page 15: ...tronic devices cannot be removed with everyday waste The correct recycling of devices gives the possibility of keeping natural resources of the Earth for a longer time and prevents the degradation of natural environment ...

Page 16: ...DTM System spó ka z ograniczon odpowiedzialnoœci spó ka komandytowa ul Brzeska 7 85 145 Bydgoszcz Polska http www dtm pl e mail dtm dtm pl desing and production of electronic devices gate automation ...

Reviews: