17
ENGLISH
L2000012 Installation guide for DucoBox Eco (Revision E.1 | 13.05.2020)
06
Commissioning
DucoBox Eco start-up
The unit must not be powered up until everything has been connected correctly and the transit foam blocks in
the unit have been removed. This includes the air ducting systems as well as all electrical components� Failure to
connect correctly can result in irreparable damage to the DucoBox Eco or to serious physical injury!
Switch on the power to the DucoBox Eco (plug into power socket)� When the DucoBox Eco starts up for the first time, you will be
asked to enter a few basic settings� Navigate using the arrow keys ( and ) and confirm using
enter
( )�
Next steps
After these steps, you can proceed with the following steps in order to complete the installation:
• Set system type in accordance with the chosen concept via
SETTINGS
→
SYSTEM TYPE
�
• Pairing control components to the DucoBox Eco�
• DucoBox Eco air-side calibration�
• DucoBox Eco water side calibration�
• Recommended: Settings for CH and DHW�
The DucoBox Eco will be ready for use after that�
IMPORTANT! In order to avoid contamination in ductwork and in the unit, it is advisable not to put the unit into
operation until the home is occupied� This is to prevent dust from the building phase getting into the ductwork and
the unit�
What happens in a power cut?
If the power supply to the DucoBox Eco fails, it will retain all its settings� Once power has been restored, the DucoBox Eco will start
up again and run� The correct time will need to be set again if the DucoBox Eco is without power for more than (around) 8 hours�