MK3B TIMBER FRAME
6
Step 4:
Stand up Back Wall frame and one End frame
and nail together, using two 75mm nails per join,
top and bottom. Stand remaining Frames up and
nail together. Nail in remaining .764m Nogs in
End Walls.
Step 5:
Position middle Jack Stud, centrally on End Wall
Top Plates and nail in place. Nail remaining Jack
Studs in. Position middle Ridge Beam to Jack
Stud and skew
-
nail in place using two 75mm
nails each end. Pre
-
drilling holes before nailing
will prevent timber from splitting.
Step 6:
Place intermediate Roof Beams by using Roofing
Nogs to determine correct position (see
fig. 2
).
Nail intermediate Roof Beams in place. Nail 70 x
45mm Roofing Nogs in place (End Wall).
Step 7:
Place Frame in correct position, checking the shed
is square and level. Dynabolt Frame to concrete
base as instructed on page 4.
Step 8:
Nail multigrip brackets to each of the four bottom
corners (two per corner). Use 30mm Clouts
supplied.
fig.2.
756m
664