P a g e
|
16
INSTALLATION (CONT’D)
Important
! Refer to mechanical layout to make sure you have the proper measurements or information regarding the
machine since machine height, conveyor positioning and control panel location have already been pre-determined by
Wulftec according to the specifications received.
Make sure machine is placed on a level surface before and after
unpacking and that machine structure is level as well once placed in position.
1. Unwrap machine and move uninstalled parts (conveyor runs, photoeye guards, etc.) away from main structure.
2. Move the base (main structure) and uninstalled parts to final location using the
lifting tubes (A) located on each side of the base. *If you need to rotate the
turntable, use the switch located on the brake (between the reducer and the
rotation motor ) to disengage the brake, this will facilitate the movement of the
table.
3. *If present, assemble in-cycle top sheet top frame and legs. DO NOT cut the
holding straps. Lift upright using a forklift and straps. Move to final location then, slowly “unfold” the top sheet
structure starting from top, cutting straps as it is unfolding.
4. Move the conveyors in position according to the center line (center of the
turntable).
5. Install all the conveyor electrical conduits under the conveyor using the mounting
clamps (B).
6. Connect and secure all electrical wires (photoeyes, motors, lanyard, e-stop, etc.)
according to electrical schematics.
7. Bolt entire machine and components to the floor using the anchor holes (control
panel, conveyor legs, machine legs, etc). Before bolting, make sure the machine is properly placed (location,
conveyor height, machine leveled, etc).
8. Once the machine has been placed or bolted in its location, verify the following:
Vulnerable items such as motors, transmission housing, photoeyes, limit switches,
control panel, etc.
Examine the carriage chains for proper tension. Verify that the carriage guides or
rollers are okay and lubricated.
Make sure all shipping brackets have been removed.
9. Assemble the fence kit according to the layouts found in the machine’s user guide Refer to
Installation of Fence
Handle
procedure below for proper fence handle installation. Anchor fence to the
floor. (If applicable).
10. Route the liquid tight wire runs along the fence and connect the quick plugs on
the back side of the electrical enclosure. If desired, attach extra length to the
fencing using multi-purpose ties (ty-wraps). (C)
11. Install the photoeye brackets and connect the photoeyes.
12. Have a certified electrician to connect the control enclosure. Make sure the voltage is correct (refer to electrical
schematics).
C
A
B