INSTALLATION (CONT’D)
13. Plug in pneumatic components to air supply. Make sure CFM and PSI are appropriate (refer to mechanical
drawings).
14. At this point, if the necessary wires for the communication signals have been pulled, plug them in the proper
terminals according to the electrical schematics, prior to moving on with the start-up procedure. Communication
terminals are located in the bottom left side on the enclosure.
15. Power up machine.
16. Verify PLC inputs one by one, using the electrical schematics, to make sure wiring is done properly to avoid
damages to the machine.
17. Follow the steps indicated on the HMI screen (clear faults, etc.)
18. Test machine functionalities in manual mode before running the machine in automatic mode.
Once everything has been inspected and appears to be in good order and operator training is done, the machine is
now ready to work. The wrapper must only be operated and serviced by authorized, trained and instructed
personnel.