GENERAL INFORMATION

STANDARDS AND REGULATIONS

The relevant regulations applicable at the 
installation site must be determined by 
the assembly company in question. The 
ceilings marketed by durlum conform to 
EN  13964. This standard also governs fire 
behaviour in accordance with EN 13501.

APPLICATION

The application of durlum metal ceilings is 
restricted, unless agreed upon otherwise, 
to interiors, so that, pursuant to EN  13964, 
class of use 1, corrosion protection class 
A, has been defined here as standard. The 
use of durlum lighting is restricted to interi-
ors. The lighting complies with protection 
class IP 20, protection class 1 according to 
EN 60598-1.

Should it become necessary to adjust the 
metal ceiling panels to the building by cut-
ting, we recommend protecting the cut-
ting edges from corrosion by means of a 
paint, to maintain the corrosion protection 
class A.

QUALITY STANDARD

For material properties, dimensions, toler-
ances, colour deviations, the TAIM Direc-
tives [Technical Association of Industrial 
Metal Ceiling Manufacturers] applies.

MOUNTING SEQUENCE

1.  Prepare ceiling- and lighting installa-

tion plan or adopt architect's plan.

2.  Check ceiling lighting installation plan 

versus structural conditions.

3.  Prepare a bill of materials, including a 

suitable work plan and retrieval/order 
of the materials required.

4.  Determine the required suspension 

points in accordance with the classes 
of use of EN  13964. The correspond-
ing suspension distances for the dif-
ferent systems can be taken from the 
detailed descriptions of the individual 
ceiling systems.

5.  Establish which generally approved 

anchor is suitable. Check the raw cei-
ling and the walls. Mark the anchor 
mounting holes and drill them. Mount 
the anchors as specified by the an-
chor manufacturer and carry out ext-
raction tests using the device recom-
mended by the anchor manufacturer, 
if necessary.

6.  Use the same procedure when mount-

ing the wall brackets, mounting dis-
tance about 400–625 mm, check the 
introduction of force into the wall.

7.  Shorten intended fastening elements, 

such as the M6 threaded rod or the 
nonius hanger to the intended length 
or order the correct length and mount 
it on the raw ceiling.

8.  Usually, the panel layout should be 

started from the centre of the room, 
in order to be able to compensate 
the tolerance of the room and cut the 
panels in half, if necessary. The precise 
arrangement must always be done on 
the basis of the ceiling layout plan.

9.  durlum metal ceilings are usually pro-

vided with a cross support [primary 
profile].

10.  Use the layout plan to determine in 

which direction the cross reinforce-
ment profiles are laid, either in parallel 
to the façade [usually] or vertically to 
the façade. The cross reinforcement 
profiles should be mounted via a wall 
anchor or via a diagonal anchoring to 
prevent an axial movement. The corre-
sponding primary profiles are mount-
ed at right angles to the secondary  
profiles. To this end, the system-specific 
connecting elements are used, see 
system descriptions. The position of the 
primary profiles is established in the re-
flected ceiling plan.

11.  The metal ceiling panels are often pro-

vided with a joint tape [9x3mm], to 
make for easier tolerance compensa-
tion. Should a joint tape be used, the 
joints must also be re-aligned from 
time to time, since the joint tape also 
has tolerances. However, owing to the 
high production precision, it is also 
possible to connect the panels without 
a joint tape by using butt joints or pro-
vide them with rubber spacer naps. Al-
ways ensure that the joints are aligned.

12.  If the panels are placed on a perime-

ter trim, we recommend our F-bracket 
as bracket or as stepped F-bracket. 
The bracket secures the panel and 
protects it against lifting. The ceiling 
panel is cut with electric sheet shears 
[i.e. Treco shears] and adapted to the 
prevailing room dimensions. When cal-
culating the minimum support area 
[10mm], the dimensions of possible 
wall movement should be taken into 
account.

13.  Attachments or other loads are to be 

mounted separately. For logical rea-
sons these parts are integrated during 
the mounting process.

14.  After completion and pre-acceptance 

of the ceiling, the sequence of joints 
should be re-aligned. Soiled ceiling 
panels should be cleaned to give a 
perfect result for assembly.

Summary of Contents for LOOP TYPE 3

Page 1: ...LOOP TYPE 3 INSTALLATION MANUAL ...

Page 2: ...rlum metal ceilings are dimensioned such that they carry their own weight of the system construction plus a surface load amounting to 40N m Higher loads must be taken into account or suspended separately in the construction and the measures must be adapted to the situa tion at hand Usually built in components and loads must be suspended separately For ceiling systems that do not allow any toleranc...

Page 3: ...k the introduction of force into the wall 7 Shorten intended fastening elements such as the M6 threaded rod or the nonius hanger to the intended length or order the correct length and mount it on the raw ceiling 8 Usually the panel layout should be started from the centre of the room in order to be able to compensate the tolerance of the room and cut the panels in half if necessary The precise arr...

Page 4: ...ux rectangulaires 956 x 1 115 mm 10 2 Magnet Magnet Magnétique 4 durlum GmbH www durlum com Subject to changes of dimensions and design Errors reserved All rights reserved Issued 08 11 2016 1 2 LOOP TYPE 3 INSTALLATION MANUAL 1 2 U 1040 LOOP steel element W2053 ST V Prim ary profile AP Secondary profile AS Magnet Screw connection W2053 ST U1042 ...

Page 5: ...PUNTEO J85 LED down lights a connecting adapter PUN J085 018 Z001 is required which is glued centrally to the back of the element Attention luminaires cannot be moun ted in the area of the secondary pro files 3 Mount ballasts drivers in the ceiling vo id possibly on U 1040 4 Perform electrical connection of the driver 5 Ensure that the LOOP elements are clean and free of grease To fasten the adapt...

Page 6: ...m is not fitted with a plug wiring should be carried out by a authorised electrician 8 Prior to acceptance align the ele ments precisely if they have been mo ved by other systems Note The lumininaire must not be coated with a heat insulating material The components are fitted with electronic components which can become damaged in case of electrosta tic discharge When handling the compo nents ensur...

Page 7: ...durlum GmbH An der Wiese 5 D 79650 Schopfheim T 49 0 76 22 39 05 0 F 49 0 76 22 39 05 42 E info durlum com I www durlum com CEILING LIGHTING AMBIENCE PLAFOND LUMIERE AMBIANCE ...

Reviews: