Starting up
51
APS09_013_0404GB
5
Starting up
This section contains working steps for commissioning the machine
for the first time and on how to prepare the machine prior to use after
a longer standstill period.
Here you will be given instructions on how to check the condition of
your machine and how to carry out a test run including functional
checks.
Note
When commissioning for the first time, operating personnel should
be instructed on how to use the machine!
The entire system should be observed during the initial hours of
operation to identify possible malfunctions.
When using the Dynajet mg Plus as an emergency unit for operating
Putzmeister concrete pumps for boom and support operation,
commission as described, without water operation.
The water filter, high−pressure hose, high−pressure gun and
unloader no longer need to be checked.
Carefully check the machine regarding the work required for
conversion to an emergency unit.
5.1
Use as an emergency
hydraulic unit