Install the unit on the wall (bolts and spacers supplied) where ever convenient for your pipe 
work. Cut your existing pipe after the filter and before the return jest. Connect a BYPASS. If 
you need to clean your electrodes or replace the algaecide electrodes this will make life easier 
and it is just good maintenance to use the bypass when adding pH correction or vacuuming 
the pool.  

The Unit must be OFF!

 Now  

Check for leaks 

and circulate.

  

 

Procedure 1

: -

 

 

1.

 

Open BYPASS pipe Valve and close the eClear pipe Valves so the water will not flow 
through the eClear chambers. 

2.

 

Backwash and Rinse Filters very well. 

3.

 

Switch Multi-Valve to Circulation. Commence to circulate water. 

4.

 

Correct pH by mixing pH correction into a bucket of water and add this directly into the 
skimmer so that the solution goes through the Circulation (not through the filter) and then 
into the Pool-Water. 

5.

 

Wait 10 minutes. Switch Multi-Valve back to FILTRATION and circulate water. 

6.

 

Considering you have depleted your chlorine or Bromine levels, add 

ACTIVE OXYGEN

 

(see product label for instructions) Add directly into the skimmer. You can also add a little 
NON COPPER based algaecide. These products are used only for the first 1 or 2 weeks! 
These should be added with Multi-Valve on FILTRATION.  

7.

 

Check that all the settings on the Unit are set to HIGH. This is achieved by switching the 
pool-size  switch  -  (

Figure  2

)  to  maximum  pool  size  and 

setting  A

.  The  Potentiometer 

knob - (

Figure 3

) should be fully anti clockwise. 

 

Switch the

 Unit ON - 

(

Figure 7

) Make 

sure the 

OXYGEN 

and  

IONIZATION 

switches are ON - (

Figure:14-15

)

  If you  have 

the UV 

(

Optional

)

 

Then also switch on the

 UV - 

(

Figure 9

)

.

 

8.

 

Check the conductivity mA meter. (

Figure 1

)

 

 Raise to 200mA for the MK7/CF1-75.   For 

the  MK7/CF1-150  raise  to  250mA.  This  is  achieved  by  setting  the  pool  size  switch  -  
(

Figure  2

)  to 

A  or  B

,

 

then turn the  potentiometer knob  slowly  clockwise -  (

Figure  3

).

 

This  will  also  depend on  the  conductivity  of  your  water.  If  the  dosing meter  indicates  a 
very high output  e.g.  400mA or above,  turn down  the potentiometer 

(Figure  3)

.  If the 

reading  is  still  too  high  change  the  switch  -  (

Figure  2

)  to  the 

B

  setting  to  achieve  an 

output of 200mA to 300mA maximum. 

9.

 

Run the  pool 24/7  non-stop  for  7  days an Re-Check  the pH. Correct if  necessary. Check 
the copper residual by following the instructions from the test kit provided. Take the water 
sample from a depth of at least 40cm and from the centre of the longest pool wall. The 
level  of  Copper  residual  required  is  between  0.5ppm  and  0.7ppm.  If  lower,  continue 
filtration 24/7 until you reach the 0.5ppm – 0.7ppm optimum Copper residual. 

10.

 

Whilst the copper residual is rising  add  a little more Active Oxygen and the  non  Metallic 
algaecide at this point.  This will keep your pool clear until the water is fully Ionised. 

11.

 

When the above readings are achieved, switch Ionization 

OFF - 

(

Figure 15

)

 

and continue 

to sanitize your pool water on the 

Oxygen Mode only 

(

Figure 14

)

.  

You will only switch 

your Ionization on again if your Copper residual drops below 0.5ppm as indicated by the 
test  kit  supplied.  If  this  happens  then  run  the  filtration  again  24/7  and  check  every  24 
hours  the  copper  level  until  you  have  achieved  again  the  0.5ppm  to  0.7ppm  copper 
residual. Otherwise you remain constantly on your Oxygen Mode. 

12.

 

Now set your filtration to Automatic and the hours necessary. 

13.

 

Follow water maintenance weekly programme supplied. 

 

 

 
 
 
 
 
 
 

Summary of Contents for MK7/CF1-150

Page 1: ...m here onwards 5 If the above is adhered to you will have a trouble free pool that will last for years and years This will also make your initial start up very easy REQUIRED FOR WATER SET UP BEFOR SWITCH ON 1 5 10 litres of Active Oxygen Depending on pool size 2 5 10 litres of non copper based algaecide Depending on pool size 3 Non metallic floc cubes optional FOR YOUR REFERENCE DIAGRAM ATTACHED C...

Page 2: ...the UV Optional Then also switch on the UV Figure 9 8 Check the conductivity mA meter Figure 1 Raise to 200mA for the MK7 CF1 75 For the MK7 CF1 150 raise to 250mA This is achieved by setting the pool size switch Figure 2 to A or B then turn the potentiometer knob slowly clockwise Figure 3 This will also depend on the conductivity of your water If the dosing meter indicates a very high output e g ...

Page 3: ...e Calcium NOTE It could take as long as 2 weeks to finally obtain clear consistent water REMEDY This is a short term and initial set up problem meaning that you did not confirm your pool shell and filtration system with us prior to installation for full advice If your tiled pool has sound grouting the filter sand is new and the pipes have been cleaned then your pool is being detoxified The natural...

Page 4: ... on Bypass and switched OFF 3 Use house hold bleach at 4 Litres per 50m3 and per week 4 Add a Non Metallic Algaecide through the skimmer at 1 Litre per 40m3 each week for 3 weeks 5 Add 1 Action Cube or Non Metallic filter flocculent in to the pump Pre Filter Replace when used 6 Back Wash and rinse filters after 24 Hours then once each week 7 After 3 weeks go to number 3 of PROCEDURE 1 NOTE If you ...