Hardware Installation
Hardware Installation
Installation Steps
1.
Unpack the switch.
2.
Check if the DIN rail clip is screwed on the Industrial switch or not. If the DIN rail clip
is not screwed onto switch, please refer to
DIN-Rail Mounting
section for DIN-Rail
installation. If the user wants to wall mount or panel mount the switch, then please refer
to
Wall or Panel Mount Plate Mounting
section for wall plate installation.
3.
To hang the Industrial switch on the DIN-Rail track or wall, please refer to the
Mounting Installation
section.
4.
Power on the Industrial switch. Please refer to the
Wiring the Power Inputs
section for
knowing the information about how to wire the power. The power LED on the Industrial
switch will light up. Please refer to the
LED Indicators
section for indication of LED
lights.
5.
Prepare the twisted-pair, straight through Category 5/above cable for Ethernet
connection.
6.
Insert one end of UTP/STP cable into the Industrial switch RJ-45 port and the other end
to the network device’s RJ-45 port, e.g. Switch PC or Server. The RJ-45 port LED on
the Industrial switch will light up when the cable is connected with the network device.
Please refer to the
LED Indicators
section for LED light indication.
7.
When all connections are set and LED lights all show in normal, the installation is
complete.
16
Manual Documentation Number EIR410-2SFP-T – 0109m
www.bb-elec.com
www.bb-europe.com