background image

 

European Safety Systems Ltd.

   Impress House, Mansell Road, Acton, London W3 7QH

 

www.e2s.com

 

Tel: +44 (0)208 743 8880

 

Document No. D199-00-501-IS

 

Issue 4

 

04-01-21

 

 

Sheet 3 of 5

 

 

 

Fig. 2: Fixing Location for Junction Box.

 

 

5.2. Access to the Flameproof Enclosure

 

 

 

 

In order to connect cabling in the junction box it is necessary 
to  remove  the  flameproof  cover  to  gain  access  to  the 
flameproof chamber. To access the Ex d chamber, loosen the 
M4 grub screw on the junction box cover. Open the enclosure 
by turning the junction box cover counterclockwise and remove 
the cover taking extreme care not to damage the flameproof 
threads in the process (see figure 3). 

 

Fig. 3: Accessing the Explosion Proof Enclosure.

 

 
On  completion  of  the  installation,  the  flameproof  threaded 
joints should  be  inspected to ensure  that  they are clean  and 
that they have not been damaged during installation. 
 
Flameproof threaded joints are not permitted to be repaired. 
 
Ensure 

that the ‘O’ ring seal is in place.

 

 
When  replacing  the  flameproof  cover  ensure  the  thread  is 
engaged correctly. Fully tighten the cover all the way, ensure 
no gap is visible between the cover and base of the junction 
box enclosure. Tighten the M4 grub screw. 
 
 
 
 
 
 
 
 

6)  Installation Requirements

 

 

6.1.  Installation Standards Compliance 
 

 

Warning 

 High voltage may be 

present, risk of electric shock. 
DO NOT open when energised, 
disconnect power before opening.

 

 
The  beacon  must  only  be  installed  by  suitably  qualified 
personnel in accordance with the latest issues of the relevant 
standards. 
 
ATEX / IECEx installation standards: 

 

EN60079-14  /  IEC60079-14:  Explosive  atmospheres  -  
Electrical installations design, selection and erection.

 

 

EN60079-10-1 / IEC60079-10-1: Explosive atmospheres - 
Classification of areas. Explosive gas atmospheres.

 

 

EN60079-10-2 / IEC60079-10-2: Explosive atmospheres - 
Classification of areas. Explosive dust atmospheres. 

 

NEC Class / Zone, CEC Class / Zone, and NEC & CEC Class 
/ Division installation standards: 

 
National Electrical Code, NFPA 70 or CSA 22.1 Canadian 
Electrical  Code,  Part  I,  Safety  Standard  for  Electrical 
Installations, Section 32. 

 

The installation of  the units must also be in accordance  with 
any local codes that may apply and should only be carried out 
by  a  competent  electrical  engineer  who  has  the  necessary 
training. 
 
The STExJ2 is not intended for directly supporting live parts. 
All conductors must be suitably insulated and secured against 
loosening. 

 

The Junction Box may be fitted with terminal blocks or active 
modules up to a power consumption of 5W. Any module fitted 
must  be  secured  to  the  mounting  bosses  in  the  base  of  the 
junction box and must maintain a minimum gap of 10mm to all 
walls of the enclosure. 
 

6.2. Cable Selection and Connections 

 
When selecting the cable size, consideration must be given to 
the input current that each unit draws (see table 1), the number 
of junction boxes on the line and the length of the cable runs. 
The cable size selected must have the necessary capacity to 
provide the input current to all of the junction boxes connected 
to the line. 
 
Electrical connections are to be made into the terminal blocks 
in the flameproof enclosure (see figure 5 and figure 6), using 
solid wire 0.5-4mm2 / AWG 20-12 or stranded wire, sizes 0.5-
2.5mm2  /  AWG  24-14.  Wire  insulation  needs  to  be  stripped 
8mm. Wires may be fitted securely with crimped ferrules. 
 

 

Figure 4: Wire Preparation.

 

 
Terminal screws need to be tightened down with a tightening 
torque of 0.45 Nm / 5 Lb-in. 
 

Warning 

 

Hot surfaces. External surfaces 

and internal components may be hot after 
operation, take care when handling the 
equipment. 

Summary of Contents for STExJ2

Page 1: ...EC60079 0 2011 Ed 6 Explosive Atmospheres Equipment General requirements EN60079 1 2014 IEC60079 1 2014 Ed 7 Explosive Atmospheres Equipment protection by flameproof enclosures d BS EN 60079 31 2014 I...

Page 2: ...likely to occur in normal operation Zone 22 ATEX IECEx only Explosive dust air mixture not likely to occur in normal operation and if it does it will only exist for a short time Gas Groupings Group I...

Page 3: ...ve atmospheres Classification of areas Explosive gas atmospheres EN60079 10 2 IEC60079 10 2 Explosive atmospheres Classification of areas Explosive dust atmospheres NEC Class Zone CEC Class Zone and N...

Page 4: ...y or 60 C at branching point Therefore suitable heat resisting cables and cable glands must be used with a rated service temperature at least as stated in the Instructions document of the product bein...

Page 5: ...el in accordance with the current relevant standards EN60079 19 IEC60079 19 Explosive atmospheres Equipment repair overhaul and reclamation EN 60079 17 IEC60079 17 Explosive atmospheres Electrical ins...

Page 6: ...Netherlands B V Utrechtseweg 310 6812 AR Arnhem Netherlands Quality Assurance Notification Module D SIRA 05 ATEX M342 Provisions fulfilled by the equipment II 2G Ex db IIC T6 T3 Gb II 2D Ex tb IIIC T...

Page 7: ...e and Place of Issue London 03 12 2021 EU Declaration of Conformity On behalf of European Safety Systems Ltd I declare that on the date the equipment accompanied by this declaration is placed on the m...

Reviews: