8
Attention: before starting fan, please make sure the dust cover on top of enclosure is
removed.
(2) Load:
Calculate the total power which needs to be loaded, then press and combine
the power values needed (they will light up when pressed). Then push the
<Load/Unload >
switch. The yellow indicator lights up and the machine loads in
accordance with the appropriate power level.
Example: Suppose you want to load 15 kW total. Press the control panel on the 5 kW &
10 kW switches to get to 15kW. Then press the <Load/Unload> switch.
If you need to change the loading power, please press the power setting switches
accordingly. You may re-combine load profile and press
< Load/Unload >
to begin
again.
Attention: To protect the system, please make sure any new load is not less than 70% of
the existing load.
(3) Stop:
If you need to end the test, press
< Load/Unload >
and remove the entire load
via the power setting switches.
4.5 Data Display
(1) Meter Symbol Description:
In the loading process, the machine can display real-
time parameters by measuring instruments. Display instrument operating diagram is
shown as follows: