SCW-410-QS (05/12)
Page 25
Figure 18. Typical Final Charge Set-up for SC, SD and SCW Compressor Units
(SC Model shown).
9. Next, the TXV is to be adjusted to provide 10°F to 20°F (or less) superheat while
running in cooling mode. The first step is to utilize the access port and LP gage in
Figure 19 to measure suction pressure.
Next, apply a thermocouple at the
compressor suction port
as shown in Figure 19, by attaching the thermocouple lead
with electrical tape, and wrapping with ½” thick insulation.
Summary of Contents for SCW R-410A
Page 8: ...SCW 410 QS 05 12 Page 8...
Page 9: ...SCW 410 QS 05 12 Page 9 Figure 5 SCW Connections for R 410A...
Page 10: ...SCW 410 QS 05 12 Page 10 Figure 6 SCW Internal Flow Schematic...
Page 11: ...SCW 410 QS 05 12 Page 11 Figure 7 SCW Piping...
Page 15: ...SCW 410 QS 05 12 Page 15 Figure 10 SCW Electrical Ladder Diagram 230 1 60...
Page 16: ...SCW 410 QS 05 12 Page 16 Figure 11 SCW Electrical Schematic 230 1 60...
Page 17: ...SCW 410 QS 05 12 Page 17 Figure 12 SCW Series 230 3 60 Electrical Ladder Diagram...
Page 18: ...SCW 410 QS 05 12 Page 18 Figure 13 SCW Series 230 3 60 Electrical Schematic...
Page 19: ...SCW 410 QS 05 12 Page 19 Figure 14 Part 1 of 2 SCW Field Wiring Diagram Reference Figure 8...
Page 20: ...SCW 410 QS 05 12 Page 20 Figure 14 Part 2 of 2 SCW Field Wiring Diagram Reference Figure 9...
Page 28: ...SCW 410 QS 05 12 Page 28 Figure 21 Charging and Superheat Adjustment Process...