Annex A Installation of internal battery
For 10kVA to 30kVA standard UPS, the internal batteries is not provided as standard;
if required, please contact your local agency.
There are 20 batteries of 9AH to be installed for 10kVA.
There are 40 batteries of 7/9AH to be installed for 15/20kVA.
There are 60 batteries of 9AH to be installed for 30kVA.
Fig.6-1 is the installation of battery of the 10kVA standard UPS.
1
.
Dismantle the covers and crossbeams
2
.
Install battery and fix the crossbeams
3.Connect the battery cable according
4
.
Recover the cover
to the series number,
Fig.6-1
Installation of battery the 10kVA standard UPS