3.3.2 Rack Installation
1. Various installation configurations are available: single UPS, single UPS with
single or multiple-battery. Their installation methods are all the same.
2. Because battery cabinets are too heavy, they must be installed first, and two or
more installation personnel are required to install them at the same time. Please install
them from bottom to top.
Rack installation: fix the UPS and battery cabinet onto the rack through brackets.
Installation method:
1. Fix the brackets onto the UPS with the screws, as shown in Fig.3-4.
Fig.3-4 Installing brackets
2. Place the UPS and battery cabinet onto the guide rail in the rack, push it completely
into the rack along the guide rail (it is prohibited to move the UPS through the
brackets). Fix the units to the service rack, as shown in Fig.3-5.
Fig.3-5 Installing UPS
3.4 Battery
Three terminals
(
positive
,
neutral
,
negative
)
are drawn from the battery unit and
connected to UPS system. The neutral line is drawn from the middle of the batteries in
series (See Fig.3-6).
Select total number of batteries from 30 to 44 (even number), and the number of
positive and negative battery strings must be consistent. 10kVA could select the total
number 20pcs.
30kVA connect to the battery with Anderson connectors (See Fig.3-2).