Action
Yes/No
All power cables are properly sized and terminated.
Neutral conductors are installed and bonded to ground according to the
requirements.
A ground conductor is properly installed.
Battery cables are terminated and connected to battery connectors.
Battery Shunt trip and Aux contact signal wiring is connected from the
UPS to the battery breaker.
LAN drops are installed.
All LAN connections are completed.
Air conditioning equipment is installed and operating correctly.
There is adequate workspace around the UPS and other cabinets.
Adequate lighting is provided around all the UPS equipment.
A 230 VAC service outlet is located within 7.5 meters of the UPS
equipment.
The Remote Emergency Power-off (REPO) device is mounted in its
installed location and its wiring is terminated inside the UPS cabinet.
If EPO is used in the NC configuration, a jumper is installed on the EPO
between pins 3 and 4.
(OPTIONAL) Alarm relays and signal outputs are wired appropriately.
(OPTIONAL) A remote battery disconnect control is mounted in its
installed location and its wiring is terminated inside the UPS and
battery cabinet.
(OPTIONAL) Accessories are mounted in their installed locations and
their wiring is terminated inside the UPS cabinet.
Start-up and operational checks are performed by an authorized Eaton
Field Service Engineer.
© Eaton Corporation plc 2020. All rights reserved.
Revision: 006
Document ID: P-164000493
36 (126)
Eaton 91PS/93PS UPS 8–40 kW
User’s and Installation Guide