Installing the UPS
3−6
EATON
Powerware
®
9315 UPS (300–500 kVA) Installation Manual
S
164201118 Rev H
www.powerware.com
3.3 Completing the Installation Checklist
The final step in installing your UPS system is completing the following installation
checklist. This checklist ensures that you have completely installed all hardware, cables, and
other equipment. Completing all items listed on the checklist will ensure a smooth
installation. You should make a copy of the installation checklist before filling it out, and
retain the original.
After the installation is complete, your service representative will be able to verify the
operation of your UPS system and commission it to support your critical load. The service
representative cannot perform any installation tasks other than verifying software and
operating setup parameters. Service personnel may request a copy of the completed
installation checklist to be sure you have completed all applicable equipment installation.
NOTE
The installation checklist MUST be completed before starting the UPS system for
the first time.
Summary of Contents for 9315
Page 1: ...Powerware 9315 UPS 300 500 kVA Installation Manual ...
Page 97: ......
Page 98: ... 164201118H 164201118 H ...