Remove the two M10 bolts securing the front shipping bracket and remove the bracket.
If needed, adjust the leveling feet to release the bracket.
Figure 8. Removing the Front Shipping Bracket and Shipping Pad
Front Shipping
Bracket
Shipping Pad
M10 Bolts
M10 Bolts
9.
Reinstall the front cover removed in
.
Hang the top edge of the cover on the cabinet first, then lower the bottom edge and snap into place.
NOTE
Support the front and back of the cabinet when rolling it off the pallet to prevent tipping.
10. Slowly roll the cabinet toward the rear of the pallet. Once the pallet tilts, continue rolling the cabinet down
the pallet until the cabinet touches the floor (see
).
If needed, adjust the leveling feet so that the cabinet rolls freely.
Summary of Contents for 9355 Series
Page 1: ...p n 164201601 Revision E0 10 15 kVA User s Guide Eaton 9355 Parallel UPS ...
Page 4: ......
Page 10: ...x Eaton 9355 Parallel UPS 10 15 kVA User s Guide 164201601 Rev E0 List of Tables ...
Page 18: ...8 Eaton 9355 Parallel UPS 10 15 kVA User s Guide 164201601 Rev E0 Safety Warnings ...
Page 54: ...44 Eaton 9355 Parallel UPS 10 15 kVA User s Guide 164201601 Rev E0 UPS System Installation ...
Page 68: ...58 Eaton 9355 Parallel UPS 10 15 kVA User s Guide 164201601 Rev E0 Operation ...
Page 72: ...164201601E0 164201601 E0 ...