INSTALLING THE UPS SYSTEM
Eaton
®
9390 UPS (20–80 kVA) and 9390IT (20-40 kVA) Installation and Operation Manual
S
164201603 Rev 4
www.eaton.com/powerquality
4-15
18.
When all wiring is complete, reinstall the safety shield panels removed in
previous steps. Secure with the retained hardware.
19.
Close the control panel door and secure with the retained hardware.
20.
Reinstall the door removed in Step 3 and secure with the retained hardware.
21.
Close the door and secure the latch.
4.8.3
X-Slot Connections
NOTE
LAN and telephone drops for use with X-Slot connectivity cards must be provided by facility planners
or the customer.
NOTE
When installing external wiring to X-Slot cards, conduit must be installed to the UPS cabinet. When
installing internal wiring to X-Slot terminals, route the wiring through the internal opening in the X-Slot
communication bay.
For installation and setup of an X-Slot card, please contact Eaton (see page 1-8).
To install wiring for connections:
1.
If not already installed, install the LAN and telephone drops.
2.
Unfasten the front door latch and swing the door open.
3.
Remove the front door from the cabinet. Retain the hardware for reinstallation.
4.
Remove the UPS cabinet X-Slot conduit landing plate to drill or punch conduit
holes (see Drawing 164201603-7 on page A-36).
5.
Reinstall the conduit landing plate and install the conduit.
6.
Route and install the LAN, telephone, and other cables to the appropriate X-Slot
cards.
7.
When all wiring is complete, reinstall the safety shield panels removed in
previous steps. Secure with the retained hardware.
8.
Close the control panel door and secure with the retained hardware.
9.
Reinstall the door removed in Step 3 or paragraph 4.2 and secure with the
retained hardware.
10.
Close the door and secure the latch.
11.
Refer to the manual supplied with the X-Slot card for operator instructions.