Eaton 93E Integrated Transformer Cabinet (ITC) Installation Manual P-164000074—Rev 3
www.eaton.com/powerquality
3-1
Chapter 3
Installation Plan and Unpacking
Use the following basic sequence of steps to install the Eaton 93E 30 or Eaton 93E 60 Integrated Transformer
Cabinet (ITC):
1.
Create an installation plan for the ITC (Chapter 3).
2.
Prepare your site for the ITC (Chapter 3).
3.
Inspect and unpack the ITC (Chapter 3).
4.
Unload and install the ITC, and wire the system (Chapter 4).
5.
Complete the Installation Checklist (Chapter 4).
6.
Have authorized service personnel perform preliminary operational checks and start up the system.
3.1
Creating an Installation Plan
Before installing the ITC, read and understand how this manual applies to the system being installed. Use the
procedures and illustrations in this section to create a logical plan for installing the ITC. This section contains
the following information:
l
Physical features and requirements, including dimensions
l
Power wiring installation notes
l
Location of conduit and wire entry landing plates
l
Location of power terminals
3.2
Preparing the Site
For the UPS system to operate at peak efficiency, the installation site should meet the environmental
parameters outlined in this manual. If the UPS system is to be operated at an altitude higher than 1500m
(5000 ft), contact an Eaton service representative for important information about high altitude operation. The
operating environment must meet the weight, clearance, and environmental requirements specified for the
applicable accessory cabinet.
3.2.1
Environmental and Installation Considerations
The UPS system installation, including the ITC, must meet the following guidelines:
l
The system must be installed on a level floor suitable for computer or electronic equipment.
l
The system must be installed in a temperature and humidity controlled indoor area free of conductive
contaminants.
Failure to follow guidelines may void your warranty.
The ITC operating environment must accommodate the weight requirements shown in Table 3-1 and the size
requirements shown in Figure 3-1 through Figure 3-6.
NOTE
Startup and operational checks must be performed by an authorized Eaton
Customer Service Engineer, or the warranty terms specified on page W-1 become
void. This service is offered as part of the sales contract for the UPS. Contact an
Eaton service representative in advance (usually a two-week notice is required) to
reserve a preferred startup date.