Installation
4-20
Eaton 93E Integrated Transformer Cabinet (ITC) Installation Manual P-164000074—Rev 3
www.eaton.com/powerquality
Figure 4-18. ITC Power Terminal Cover Splice Installation
4.4.2
Single-Feed UPS with Input and Output Transformers
To install wiring to connections:
1.
If not already open, open the front door by lifting the latch from the bottom and turning to the right
(counterclockwise) and swing the door open (see Figure 4-1 or Figure 4-4).
2.
Remove the screws securing the internal safety shield panel and remove the panel to gain access to the
input and output breaker terminals. Retain the hardware for later use.
3.
Install conduit between the utility source and the ITC.
93E 30ITC
93E 30 kVA UPS
Power Terminal Cover
Right Side Installed
Power Terminal Cover
Top Installed
Power Terminal Cover
Splice Installed
Power Terminal Cover
Left Side Installed
Power Terminal
Cover Top Installed
NOTE 1
The 93E 30ITC and 93E 30 kVA UPS are shown. The 93E 60ITC and 93E 60 kVA UPS
installation is the same.
NOTE 2
The UPS and ITC are shown adjacent, but other installed accessory cabinets may be
adjacent in large systems with multiple cabinets. However, the cover splice installation is the
same.
NOTE 3
Do not install the Power Terminal Cover Left and/or Right Side covers if wiring adjacent
cabinets using the power terminal base wiring channel.