Figure 30. Normally-closed remote EPO switch wiring
A Remote EPO switch (N.C.)
C
UPS Remote EPO terminal (REPO)
B Twisted wires
5.5 Initial startup
Startup and operational checks for a single UPS installation must be performed
by an authorized Eaton Customer Service Engineer or other qualified service
personnel such as a licensed service engineer from an agent authorized by the
manufacturer.
Startup and operational checks for parallel systems or installations with
accessory cabinets must be performed by an authorised Eaton Customer
Service Engineer, or the warranty terms specified in Chapter
This service is offered as part of the sales contract for the UPS. Contact an
Eaton service representative in advance (usually a two-week notice is required)
to reserve a preferred startup date.
5.6 Completing the installation checklist
The final step in installing the UPS system is completing the installation
checklist, see Section
. This checklist ensures that you have completely
installed all the hardware, cables, and other equipment. Complete all the items
listed in the checklist to ensure a smooth installation. Make a copy of the
installation checklist before filling it out, and retain the original.
After the installation is completed, an Eaton Customer Service Engineer must
verify the operation of the UPS system and commission it to support the critical
load. The service representative cannot perform any installation tasks other than
verifying the software and the operating setup parameters. Service personnel
may request a copy of the completed installation checklist to verify that all the
applicable equipment installations have been completed.