UPS Installation Plan and Unpacking
3-6
Eaton 93E UPS (300/400 kVA, 380/400/415V) Installation and Operation Manual
•
Parallel UPS input wiring size requirements and output wiring size requirements from the UPSs to the Tie
Cabinet are the sames as those for single systems.
•
This device is not equipped with its own mains separation device. It is , therefore, essential that the customer
install such a device at the installation site near the UPS.
•
Install a proper three-pole overcurrent disconnect device or four-pole overcurrent disconnect device before
connecting to the UPS, the disconnect device shall disconnect simultaneously all line conductors of the AC
MAINS SUPPLY.
•
The UPS requires an input neutral connection. Ensure that an input neutral is connected prior to energising
the UPS. If a 4 pole Automatic Transfer Switch is installed upstream of the UPS it must work with a break
before make transition with a minimum transfer time of 50ms.
Figure 4-6 and Figure 4-7 show the location of the UPS power cable terminals.
Summary of Contents for 93E
Page 1: ...300 400 kVA 380 400 415V Installation and Operation Manual Eaton 93E UPS...
Page 2: ......
Page 4: ......
Page 19: ...Section 1 Installation...
Page 20: ......
Page 49: ...Section 2 Operation...
Page 50: ......
Page 91: ......
Page 92: ...614 08137 00...