Eaton 93PM Sidecar Integrated Accessory Cabinet-Bypass (50 kW and 100 kW SIAC-B) Installation and Operation Manual P-164000230—Rev 09
47
44..99
IInniittiiaall S
Sttaarrttuupp
NOTE
Startup and operational checks must be performed by an authorized Eaton Customer
Service Engineer, or the warranty terms specified on the product's resources page
become void. See
for details. This service is offered as part of the
sales contract for the UPS. Contact an Eaton service representative in advance (a
minimum two-week notice is required) to reserve a preferred startup date.
44..1100
C
Coom
mpplleettiinngg tthhee IInnssttaallllaattiioonn C
Chheecckklliisstt
The final step in installing the SIAC-B is completing the following Installation Checklist. This checklist ensures
that you have completely installed all hardware, cables, and other equipment. Complete all items listed on the
checklist to ensure a smooth installation. Make a copy of the Installation Checklist before filling it out, and
retain the original.
After the installation is complete, an Eaton Customer Service Engineer must verify the operation of the UPS
system and commission it to support the critical load. The service representative cannot perform any
installation tasks other than verifying software and operating setup parameters. Service personnel may request
a copy of the completed Installation Checklist to verify all applicable equipment installations have been
completed.
NOTE
The Installation Checklist MUST be completed prior to starting the UPS system for the
first time.
44..1111
IInnssttaallllaattiioonn C
Chheecckklliisstt
o
All packing materials and restraints have been removed from each cabinet.
o
The system is installed on a level floor suitable for computer or electronic equipment.
o
All conduits and cables are properly routed between the SIAC-B and the UPS.
o
All power cables are properly sized and terminated.
o
A ground conductor is properly installed.
o
All terminal conductor plates are installed.
o
Air conditioning equipment is installed and operating correctly.
o
The area around the UPS system is clean and dust-free.
o
Adequate workspace exists around the SIAC-B and other cabinets.
o
Adequate lighting is provided around all SIAC-B and UPS equipment.
o
A 120 Vac service outlet is located within 7.5 meters (25 feet) of the SIAC-B and UPS equipment.
o
Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.
o
Visit
www.eaton.com/pq/register
to register your new Eaton UPS / Eaton UPS Accessory.