Introduction
1-2
Eaton 93PM Integrated Battery Cabinet-Small Welded (IBC-SW) Installation Manual P-164000639—Rev 1
www.eaton.com/powerquality
1.1
Installation Features
l
Line-up-and-match configurations using factory supplied power wiring or standalone configurations using
customer supplied power wiring
l
Battery wiring can be run internally through the left or right sides of the IBC–SWs in line-up-and-match
configurations, or routed through the top or bottom of the IBC–SWs using conduit in standalone
configurations
l
Front access panel for access to the battery breaker
l
Interface wiring can be routed through the top left or right sides of the IBC–SWs in line-up-and-match
configurations or through the top or bottom of the IBC–SWs using conduit in standalone configurations
l
Built-in casters for easy cabinet placement
Line-up-and-match battery cabinets are installed adjacent to the UPS. The IBC-SW can be installed on either
the left or right side or on both sides of the UPS cabinet (see Figure 1-2).
Figure 1-2. Eaton 93PM UPS and Two 93PM IBC–SWs Left Side, Right Side, or Combination Installation
UPS
Right Side IBC-SW Installation
UPS
IBC-SW 1
IBC-SW 2
IBC-SW 2
Left Side IBC-SW Installation
IBC-SW 1
Combination
Left and Right Side IBC-SW
Installation
UPS
IBC-SW 2
IBC-SW 1