Installation
4-8
Eaton 93PM Integrated Battery Cabinet-Small Welded (IBC-SW) Installation Manual P-164000639—Rev 1
www.eaton.com/powerquality
8.
Connect the positive, negative, and ground power wiring from the IBC–SW to the UPS cabinet external
battery input and ground terminals. Refer to the applicable Eaton 93PM UPS Installation and Operation
manual listed in paragraph 1.7, for UPS cabinet termination requirements.
9.
If installing more than one IBC–SW, repeat Steps 2 through 8 for each IBC–SW, and then proceed to
paragraph 4.4; otherwise, proceed to paragraph 4.4.
NOTE
Route the battery wiring between the UPS and subsequent IBC–SWs through the
bottom of the adjacent IBC–SW.
NOTE
The internal battery string is to be connected by an authorized Eaton Customer
Service Engineer at system startup.