42
Eaton 93PM Universal Integrated Battery Cabinet (IBC-LW and IBC-LHW) Installation Manual P-164000541—Rev 04
to mounting. Install the conduit plate and install all conduit runs into the plate. Pull the wiring through the
conduit into the wiring area.
14. During the wiring process you may need to move the Battery Breaker assembly which is mounted on a
sliding bracket. To move the assembly, loosen the screw located beneath the breaker and then press the
lever on top of the bracket (see
) and slide the breaker to the left.
NOTE
The breaker assembly must be mounted to the right side in order for the internal safety
shield to be installed.
Figure 17. DC Power Terminal — Top Wiring Entry Terminal Installation
Top Entry Wiring
(Remote Installation Only)
DC Output Power Terminals
Configuration
[Shield Removed]
Summary of Contents for 93PM IBC-LW
Page 4: ......
Page 78: ...P 16400054104 P 164000541 04...