Eaton 93PM-L 20 – 60 kW (208V) UPS Installation and Operation Manual P-164000711—Rev 03
97
Table 28. Normally-Closed REPO Connections and Wire Terminations
From REPO
Station
Switch Con-
tact Block
(Either
Block)
UPS
REPO
Terminal
Nam-
e
Description
Recommended
Minimum
Wire Size
Size of Wire
Termination
Tightening
Torque
3 NO
1
EPO_
A_B
Input: Normally-closed
dry contact used to
activate UPS EPO from
a remote switch.
Twisted Pair Wires #18
AWG
#16 #30 AWG
2 lb in
(0.22-0.25 Nm)
4 NO
2
GND-
ISO
Figure 48. Normally-Closed REPO Switch Wiring
3
1
2
4
1
2
REPO
Switch
(NC)
Twisted
Wires
REPO TB
44..88
IInniittiiaall S
Sttaarrttuupp
Startup may be performed by the customer’s battery qualified electrical contractor for single (not parallel) UPS
installations without any accessory cabinets such as an External Battery Cabinet.
Startup and operational checks for parallel systems or installations with accessory cabinets must be performed
by an authorized Eaton Customer Service Engineer, or the warranty terms specified on the product's resources
page become void. See
for details. This service is offered as part of the sales contract for
the UPS. Contact an Eaton service representative in advance (usually a two-week notice is required) to reserve
a preferred startup date.
44..99
C
Coom
mpplleettiinngg tthhee IInnssttaallllaattiioonn C
Chheecckklliisstt
The final step in installing the UPS system is completing the following Installation Checklist. This checklist
ensures that you have completely installed all hardware, cables, and other equipment. Complete all items listed
on the checklist to ensure a smooth installation. Make a copy of the Installation Checklist before filling it out,
and retain the original.
Summary of Contents for 93PM-L 60-1
Page 4: ......
Page 164: ...P 16400071103 P 164000711 03 ...