1.
Verify the UPS system is turned off and all power sources are removed. See Chapter 6, “UPS Operating
Instructions,“ for shutdown instructions.
2.
If not already opened, open the front door by lifting the latch from the bottom and turning to the right
(counterclockwise) and swing the door open.
3.
If wiring the battery detect connections using the inter-cabinet wiring access pass-through (line-up-and-
match configurations), proceed to
; if wiring the battery interface connections using bottom entry
access, proceed to
; if wiring the battery interface connections using top entry access, proceed to
4.
Pass-through Wiring.
Route the battery detect wiring from the battery cabinet through the top UPS inter-
cabinet wiring access pass-through to the UPS building alarm terminals. See
for UPS wiring
access information, and
and
for UPS terminal locations. Refer to the
Eaton 93PM
Integrated Battery Cabinet Installation Manual-Large and Large High Rate
, the
Eaton 93PM Universal
Integrated Battery Cabinet Installation Manual-Large and Large High Rate
, or the
Eaton 93PM Integrated
Battery Cabinet-Small Welded IBC-SW (432V and 480V) Installation Manual
, listed in paragraph 1.8, for
battery cabinet wiring access information and instructions.
5.
Proceed to
6.
Bottom Entry Wiring.
Remove the bottom interface entry conduit landing plate to drill or punch holes
(see
).
7.
Reinstall the interface entry plate and install the conduit.
8.
Route the battery detect wiring from the battery cabinet through the bottom interface entry conduit
landing plate to the bottom access interface wiring channel along the inside of the front door (see
). Refer to the
Eaton 93PM Universal Integrated Battery Cabinet Installation Manual-Large and
Large High Rate
, or the
Eaton 93PM Integrated Battery Cabinet-Small Welded IBC-SW (432V and 480V)
Installation Manual
, listed in paragraph 1.8, for battery cabinet wiring access information and instructions.
9.
Route the wiring along the interface wiring channel (see
) to the UPS building alarm terminals.
See
and
for UPS interface terminal locations.
10. Secure the wiring to the wire tie anchors provided (see
) using Zip ties.
11. Proceed to
12.
Top Entry Wiring.
Remove the top interface entry conduit landing plate to drill or punch holes (see
).
13. Reinstall the interface entry plate and install the conduit.
14. Route the battery detect wiring from the battery cabinet through the top interface entry conduit landing
plate to the UPS building alarm terminals. See
f or wiring access information, and
and
for UPS interface terminal locations. Refer to the
Eaton 93PM Universal Integrated Battery
Cabinet Installation Manual-Large and Large High Rate
, or the
Eaton 93PM Integrated Battery Cabinet-
Small Welded IBC-SW (432V and 480V) Installation Manual
, listed in paragraph , for battery cabinet wiring
access information and instructions.
15. Connect the battery detect wiring to one pair of building alarm terminals. See paragraph
Installing Battery Detect Interface Connections
and for wiring and termination requirements, and for
terminal assignments.
16. If wiring battery shunt trip connections, proceed to paragraph
Installing Battery Shunt Trip Interface Connections
; if wiring bypass shunt trip connections, proceed
to paragraph
Installing Bypass Shunt Trip Interface Connections
; if wiring generator interface
connections, proceed to paragraph
Generator Interface Connections
; if wiring Minislot connections,
proceed to paragraph
Installing Minislot Interface Connections
; if wiring REPO connections, proceed
to paragraph
; otherwise, proceed to
17. Close the UPS outside door and secure the latch.
Summary of Contents for 93PM-L IAC-B