Eaton 93PM-L 20 – 60 kW (208V) UPS Installation and Operation Manual P-164000711—Rev 03
45
Table 15. Recommended Installation Parts and Tools (Not Supplied by Eaton)
Part
Size
Quantity
Notes
Long Barrel 2-Hole Lug
6 AWG
As Required
Copper wire only
4 AWG
2 AWG
1 AWG
1/0 AWG
2/0 AWG
3/0 AWG
4/0 AWG
250 MCM
300 MCM
350 MCM
500 MCM
Manual Hydraulic Crimp Tool
14 Ton
1
Die Set
N/A
1
NOTE
For additional information (including part numbers and manufacturer information) and/or assistance contact an Eaton
service representative (see paragraph
Conduit sizes were chosen from NEC Table 4, Electrical Metallic Tubing (EMT). See
for conduit
recommendations.
Per NEC article 300, 3(B), all three-phase conductors must be run in the same conduit. A ground wire must be
run in the same conduit as the phase conductors.
When running parallel wires in multiple conduits a ground wire must be run in each conduit in accordance with
NEC Table 250.122.
Conduit is sized to accommodate one ground conductor per conduit, sized in accordance with
NEC Table 250.122.
Conduit sizes listed are for copper wiring only.