Eaton 93PM UPS 480V Three-Wire – 100 kW Frame Installation and Operation Manual 164000227—Rev 07
13. If a sidecar is attached to the UPS, remove the bottom screw securing the sidecar front panel. Lift the
panel straight up to remove from the panel hanger brackets at the top of the cabinet.
14. If a sidecar is attached to the UPS, remove the sidecar mounting bolts holding the front and rear sidecar
supports to the cabinet base (see
).
15. Remove the cabinet mounting bolts holding the front and rear supports to the cabinet base.
16. If installing the cabinet permanently, retain the cabinet mounting bolts; otherwise, recycle the bolts along
with the support brackets in a responsible manner.
17. Close the door and secure the latch.
18. If a sidecar is attached to the UPS, remove the screws securing sidecar rear shipping bracket. Remove the
bracket and reinstall the screws (see
).
19. If the leveling feet are not retracted, turn all four leveling feet until they are retracted as far into the cabinet
as possible.
CAUTION
To prevent tipping when rolling the cabinet, push the cabinet from the rear whenever possible.
20. Roll the cabinet to the final installation location.
21. Lower the UPS cabinet feet and using a level, adjust the cabinet height accordingly until the cabinet is
level.
22. If installing the IBC adjacent to the UPS, locate the top splice bracket shipped with the IBC; otherwise go
to
Step 25
.
23. Remove the screws along each adjacent cabinet top panel securing the top panels. Retain the hardware
for later use.
24. Install the top splice bracket between the adjacent cabinet and secure the tie strap with retained hardware.
NOTE
Either front and back floor mounting brackets or left and right side floor mounting
brackets are available for permanently mounting the UPS.
25. If permanently mounting the UPS using the left and right side floor mounting brackets, proceed to
Step
26
; if using the front and rear floor mounting brackets, proceed to
Step 30
; otherwise, proceed to
Step 33
.
26. Locate the left and right side floor mounting brackets from the floor mounting kit.
27. Using the retained cabinet mounting bolts, install the floor mounting brackets to the left and right side of
the UPS with the angle facing outward.
28. Secure the cabinet to the floor with customer-supplied hardware.
29. Proceed to paragraph
Integrated Battery Cabinet Installation
.
30. Locate the front and back floor mounting brackets from the floor mounting kit.
31. Using the retained cabinet mounting bolts, install the floor mounting brackets to the front and rear of the
UPS with the angle facing outward.
32. Secure the cabinet to the floor with customer-supplied hardware.
33. Proceed to paragraph
Integrated Battery Cabinet Installation
.
NOTE
Black cover dots are provided, if side mounting bracket holes need to be covered for
aesthetic reasons.