Eaton 93PM UPS 480V Three-Wire – 100 kW Frame Installation and Operation Manual 164000227—Rev 07
To install wiring:
1.
Verify the UPS system is turned off and all power sources are removed. See
, for shutdown instructions.
2.
If not already opened, open the front door by lifting the latch from the bottom and turning to the right
(counterclockwise) and swing the door open.
3.
If wiring the battery detect connections using the inter-cabinet wiring access pass-through (line-up-and-
match configurations), proceed to
Step 4
; if wiring the battery interface connections using bottom entry
access, proceed to
Step 6
; if wiring the battery interface connections using top entry access, proceed to
Step 12
.
Refer to the
Eaton 93PM Integrated Battery Cabinet Installation Manual – Large and Large High Rate
, the
Eaton 93PM Universal Integrated Battery Cabinet Installation Manual-Large and Large High Rate
, the
Eaton
93PM Integrated Battery Cabinet Installation Manual-Small
, or the
Eaton 93PM Integrated Battery Cabinet-
Small Welded IBC-SW (432V and 480V) Installation Manual
, listed in paragraph
for battery cabinet wiring access information and instructions.
4.
Pass-through Wiring.
Route the battery detect wiring from the battery cabinet through the top UPS inter-
cabinet wiring access pass-through to the UPS building alarm terminals. See
for UPS wiring
access information, and
and
for UPS terminal locations.
5.
Proceed to
Step 15
.
6.
Bottom Entry Wiring.
Remove the bottom interface entry conduit landing plate to drill or punch holes
(see
7.
Reinstall the interface entry plate and install the conduit.
8.
Route the battery detect wiring from the battery cabinet through the bottom interface entry conduit
landing plate to the bottom access interface wiring channel along the inside of the front door (see
).
9.
Route the wiring along the interface wiring channel to the UPS building alarm terminals. See
and
for UPS interface terminal locations.
10. Secure the wiring to the wire tie anchors provided (see
) using Zip ties.
11. Proceed to
Step 15
.
12.
Top Entry Wiring.
Remove the top interface entry conduit landing plate to drill or punch holes (see
).
13. Reinstall the interface entry plate and install the conduit.
14. Route the battery detect wiring from the battery cabinet through the top interface entry conduit landing
plate to the UPS building alarm terminals. See
for wiring access information, and
and
for UPS interface terminal locations.
15. Connect the battery detect wiring to one pair of building alarm terminals. See paragraph
UPS System Interface Wiring Preparation
and
for wiring and termination requirements, and
for terminal assignments.
16. If wiring battery shunt trip connections, proceed to paragraph
Installing Battery Shunt Trip Interface Connections
; if wiring generator interface connections,
proceed to paragraph
Generator Interface Connections
; if wiring external parallel CAN connections,
proceed to paragraph
Installing External Parallel CAN Control Wiring and Connections
; if wiring
external parallel pull chain connections, proceed to paragraph
Installing External Parallel Pull Chain Control Wiring and Connections
; if wiring Minislot connections,
proceed to paragraph
Installing Minislot Interface Connections
; if wiring REPO connections,
proceed to paragraph
; otherwise, proceed to
Step 17
.
17. Close the UPS outside door and secure the latch.