4.6. UPS System Installation (600 kW)
4.6.1. Mechanically joining the Cabinet Sections
NOTE
•
For the following steps, verify that the forklift or pallet jack is rated to handle the
weight of the cabinet (see
• Do not tilt the UPS cabinets more than 10° from vertical or the cabinets may tip over.
1. Remove the front and rear baffle Plates of the UPS cabinets. Please keep the baffle Plates
and screws for later use;
See
for the location of the baffle Plates;
2. Use the holes on the feet. Place the UPS cabinets on the ground or channel steel;
See
and
bottom view for hole dimensions, For more detailed installation drawings, please
contact customer service to provide;
3. Fix the cabinet foot to the floor or channel steel, reinstall the baffle Plates, and use the
M10*25 bolt (16pc)/M10 spring washer (16pc)/M10 large flat washer (16pc) removed in step
1 to fix it. Torque: 28 Nm;
4. If installing a parallel system, repeat the above steps to all units in the system;
5.
Proceed to Section
.