NOTE
Do not strain relieve EPO or external bypass wiring with the same cable tie used for
Generator “On” wires.
EPO and external bypass circuits are safety extra low voltage circuit. This circuit must be isolated from any
hazardous voltage circuits by reinforced insulation.
3.
Attach the supplied cable connectors to the ends of the input wires.
4.
For BPE connections as shown in :
a.
Connect up the 4 wires from the BPE to the 9PXM per the attached drawing and using the 3 pin
connector (see
).
Figure 21. BPE to UPS Connector
3 2 1
4 3 2 1
4 3 2 1
4 3 2 1
7 6 5 4 3 2 1
Force Bypass
Common
On UPS
FORCED
BYPASS IN
(red wire)
BYPASS
NEUTRAL
(black wire)
ON UPS
(white wire)
b.
Install the 3 pin connector into the 9PXM UPS BPM CN13 connector (see
).
Figure 22. Three-Pin BPM to UPS Connector
FORCED
BYPASS IN
(red wire)
BYPASS
NEUTRAL
(black wire)
ON UPS
(white wire)
3 2 1
4 3 2 1
4 3 2 1
4 3 2 1
7 6 5 4 3 2 1
Force Bypass
Common
On UPS
Summary of Contents for 9PXM8S4K
Page 1: ...p n P 164000669 Revision 10 Eaton 9PXM UPS 4 20kVA Users Guide Eaton 9PXM UPS...
Page 4: ......
Page 8: ...viii 4 20kVA Users Guide P 164000669 4 20kVA Users Guide P 164000669 Rev 10 Table of Contents...
Page 12: ...xii 4 20kVA Users Guide P 164000669 4 20kVA Users Guide P 164000669 Rev 10 List of Tables...
Page 20: ...8 4 20kVA Users Guide P 164000669 4 20kVA Users Guide P 164000669 Rev 10 Physical Features...
Page 98: ...86 4 20kVA Users Guide P 164000669 4 20kVA Users Guide P 164000669 Rev 10 Display Menu Screens...
Page 104: ...92 4 20kVA Users Guide P 164000669 4 20kVA Users Guide P 164000669 Rev 10 Communication Slots...
Page 120: ...P 16400066910 P 164000669 10...