2.2 Mechanical installation
The MBP supports two installation modes: Tower installation and rack installation. The MBP
should be located at the top (rack installation), or to the left (tower installation) of the power
module for cable connection access. (as shown below)
Rack installation Tower installation
Allow for 500mm front and rear clearance from the module for ventilation
Do not carry the front/rear panel of the module during installing.
2.2.1 Rack mount
The Installation steps are the same as that of the UPS Power module. The MBP is suitable for
installation in a 19-inch standard rack cabinet. It is recommended that the depth of the cabinet
be no less than 800mm.
1.
Install the optional rail kit. This rail kit is '2U & with M5 sized screw holes, the depth of
the rail kit is: 415-763mm.
Summary of Contents for 9SX 15K Series
Page 1: ...1 Eaton 9SX 15 20K Series Maintenance ByPass MBP MBP20K MBP20KPDU MBP20KPARA...
Page 2: ...Copyright 2020 EATON All rights reserved...
Page 50: ...50...
Page 53: ...53 Appendix 1 System block diagram...
Page 55: ......
Page 56: ...614 40048 00...