Eaton Advanced ePDU User’s Guide P-164000042—Rev 1
www.eaton.com/ePDU
9
Chapter 3
Installation
All Eaton Advanced Enclosure Power Distribution Unit (ePDU) models are 0U products and are mounted
vertically inside standard rack structures. Use the information in this chapter to prepare, install, and connect the
ePDU and optional accessories.
Installation Precautions
Before you install or connect the ePDU in a rack cabinet, observe the following precautions:
l
Only a competent service person should install, test, or configure the ePDU and its optional accessories. It
is the installer’s responsibility to ensure that the selected product is installed to meet national and local
safety regulations.
l
Read and understand all warnings and cautions listed in Chapter 2, “Safety Warnings” on page 8.
l
Review the documentation that comes with your rack cabinet for safety and cabling information.
l
Verify that the room air temperature is below 50°C (122°F).
l
Take all necessary precautions to handle the weight of the devices.
l
Connect all power cords to properly wired and grounded electrical outlets.
l
Verify that the power outlet is near the equipment and is easily accessible so that the ePDU can be
disconnected quickly.
l
Do not overload the power outlet when you install multiple devices in the rack cabinet.
l
To reduce the risk of fire, connect only to a circuit provided with branch circuit overcurrent protection with an
ampere (A) rating in accordance with the National Electrical Code
®
(NEC
®
), ANSI/NFPA 70 or your local
electrical code, as listed in Table 25 on page 112.
l
Verify that all equipment is unplugged from ePDU outlets before carrying out any testing.
Inspecting the Equipment
If any equipment has been damaged during shipment, keep the shipping cartons and packing materials for the
carrier or place of purchase, and file a claim for shipping damage. If you discover damage after acceptance, file
a claim for concealed damage.
To file a claim for shipping damage or concealed damage: 1) File with the carrier within 15 days of receipt of
the equipment; 2) Send a copy of the damage claim within 15 days to your service representative.
NOTE
Removing the rack cabinet doors and side panels might make installation
easier. See the rack cabinet documentation for more information.
NOTE
The illustrations in this document might differ slightly from your hardware.