Maintenance
Copyright © 2007-2018 Eaton Corporation. All Rights Reserved.
IPN 997-00012-07A1 July 2018
59
Step 2 - Align the rectifier with the guides
Step 3 - Push in the rectifier
1
Push in the rectifier until the retaining screw contacts the shelf.
2
Check the rectifier's rear connector is correctly aligned with the shelf connector or
damage may occur.
3
Tighten the retaining screw to 1.5Nm (13.3 inch-pounds). This will locate the
rectifier in its rear connector.
4
Check that the rectifier’s Power On LED turns on (after the startup delay) and the
alarm LEDs turn off.
The rectifier will automatically register with the system controller and download its
operating parameters. No adjustments are required.
Procedure complete
Replacing or Adding a Load MCB
Step 1 - Remove covers
1
Remove the top cover, if fitted.
2
Remove the DC Distribution front cover.
Step 2 - Remove existing MCB (if required)
1
Disconnect the load cable and the fuse fail detect wire from the MCB top
terminal. Insulate the ends of both the cable and the wire.
2
Undo the bottom MCB terminal.
3
Unclip the MCB from the DIN rail and remove the MCB.