Eaton BladeUPS DoS Installation Instructions P-164000613—Rev 3
Figure 3. Unpacking a BladeUPS Shipping Carton
3.
Check each shipping carton to identify the contents.
Note:
Some of the boxes are empty. They are in the stack to prevent voids inside the shipping carton that
would allow the contents to shift. Discard per your practice, or store for future use.
Section 5
Unloading the System
Note:
Front and rear stabilizing bolts are bolted through the floor of the cabinet into the pallet to secure the
system for shipping. The bolts must be removed before unloading the system.
1.
Unlock the BladeUPS cabinet and place the key in a secure place so it will be available to you when you
need it.
2.
Open the BladeUPS cabinet front door.
3.
Ensure the UPS/Service/Bypass switch dial is turned to UPS (see Table 2 and Figure 4).
Table 2. UPS Bypass Switch Positions
Switch Position
Description
UPS
Connects the UPS output to the load.
SERVICE
Connects the load directly to AC input power and disconnects UPS output. AC
input power is still connected to the UPS input.
BYPASS
Like the SERVICE position, BYPASS connects the load directly to AC input power
and disconnects UPS output. However, because BYPASS also disconnects AC
input from the UPS, this is the appropriate position for UPS maintenance or
repair.