CH plug-on neutral (PON) circuit breaker
installation tips
Please follow these specific steps when installing Eaton’s
CH PON circuit breakers, across from one another.
•
Firmly press the load-side of each breaker all the way
down onto the neutral bar.
•
Once the load-side of each breaker is securely attached
to the neutral bar, push down on the line-side of each
breaker attaching it to the bus-stab. This makes for a
complete connection to the bus.
•
For the line-side, it is recommended to push down on
each breaker at the same time.
•
Verify the load-side meets the neutral bar, and the
line-side is centered within the loadcenter.
•
Please refer to figures 1 and 2.
•
Once confirmed the CH PON breakers have a secure
connection to the neutral bars and bus stabs, the CH
loadcenter deadfront and cover can be installed.
Figure 1
Figure 2
Figure 3
Please note:
As stated on all CH PON loadcenter interior
labels (figure 3), the neutral bar screws are not to be backed
out, and the wire is not to be installed in the neutral bar
terminals beneath the CH PON breakers.
Failure to follow
this specific instruction may prevent proper installation.