22
11. Troubleshooting Guide
EAFR-101 Arc Point Sensor Relay User Manual
MN026004EN February 2016 www.eaton.com
10.5 Test Plan Example
Date:
Substation:
Switchgear:
EAFR-101 Serial Number:
Preconditions
Light Only
Light + Current
Remarks
Sensor Channel 1 Setting
Sensor Channel 2,3,4 Setting
Master Trip Binary Input in Use (Yes / No):
Circuit Breaker Failure Protection (CBFP) in Use (Yes / No):
Object Activated
LED Indication
T1, T2, T3, and T4 Active
BO1 Active
Sensor Channel 1
Sensor 1
Sensor 2
Sensor 3
Sensor Channel 2
Sensor 1
Sensor 2
Sensor 3
Sensor Channel 3
Sensor 1
Sensor 2
Sensor 3
Sensor Channel 4
Sensor 1
Sensor 2
Sensor 3
BIN 1
BIN 2
Tested by:
Approved by:
11. Troubleshooting Guide
Table 8. Troubleshooting Guide.
Problem
Check
Cross Reference
Sensor does not acti-
vate when testing.
Sensor cable wiring
Section 4 of this manual
Camera (or other test
equipment) flash intensity
Section 10 of this
manual
Trip relay(s) does not
operate even if sensor is
activated.
Dipswitch settings
Section 3.5 of this
manual
12. Technical Data
12.1 Protection
Trip time using mechanical trip relays.
7 ms*
Reset time (arc light stage).
2 ms
Protection operational after power up.
88 ms
* = Total trip time using arc light or phase/residual over-current from
EAFR-110 and arc light.
12.2 Auxiliary Voltage
Vaux
(110-220) Vac / (125-250)
Vdc ±20%
Maximum Interruption
100 ms
Maximum Power Consumption
5 W
Standby Current
90 mA