Installation checklist
Action
Yes/No
All packing materials and restraints are removed from each cabinet.
Each cabinet in the UPS system is placed in its installed location.
A cabinet grounding kit / mounting kit is installed between any
cabinets that are bolted together.
All conduits and cables are properly routed to the UPS and any
ancillary cabinets.
All power cables are properly sized and terminated.
Neutral conductors are installed according to the requirements.
A ground conductor is properly installed.
Battery cables are terminated and connected to battery connectors.
Battery Shunt trip and Aux contact signal wiring is connected from
the UPS to the battery breaker.
Room ventilation is installed and operating correctly.
Air conditioning equipment is installed and operating correctly.
The area around the installed UPS system is clean and dust-free (it is
recommended that the UPS is installed on a level floor suitable for
computer or electronic equipment).
There is adequate workspace around the UPS and other cabinets. To
allow emergency evacuation, an escape path with a minimum width
of 600 mm must be maintained.
Adequate lighting is provided around all the UPS equipment.
A 230 VAC service outlet is located within 7.5 meters of the UPS
equipment.
(OPTIONAL) Alarm relays and signal outputs are wired appropriately.
(OPTIONAL) A remote battery disconnect control is mounted in its
installed location and its wiring is terminated inside the UPS and
battery cabinet.
(OPTIONAL) Accessories are mounted in their installed locations and
their wiring is terminated inside the UPS cabinet.
Start-up and operational checks are performed by an authorized
Eaton Customer Service Engineer.
Summary of Contents for EBC-S