24
Green Motion EV smart breaker chargers
EV WALL CHARGER AND EV WALL CHARGER PLUG-IN
www.eaton.com
STEP E-1
Dual port
EV WALL CHARGER PEDESTAL INSTALLATION
Install second EV wall charger base
E
I1B
1
2
3
STEP E-2
Dual port
• Use three 1/4-20 nuts and washers
(1 and 2)
to
secure the EV wall charger base to the cover .
• Remove and reInstall one 1/4-20 bolt
(3)
through
the EV wall charger base and into top section cover .
Hold the bolt in place while installing a washer and
locknut to the inside of the EV pedestal .
Reference:
1.
1/4-20 nylon locknut - x4
2.
1/4-20 washer - x4
3.
1/4-20 x 0.625-inch machine screw
Figure 17
• Replace the mechanical closer
(1)
.
• Install the second EV wall charger
base so that it properly aligns with the
three 1/4-20 studs protruding through
the top section cover .
• Install
conduit fitting
(2)
and o-ring
(3)
.
2
1
3
Reference:
1.
Mechanical closer
2.
1" trade size conduit fitting
3.
33 mm ID o-ring
Figure 16