2.
Assemble the frame that supports the battery cabinet as shown in
Figure 6. Leave all bolts finger-tight until the frame is sized for the
rack.
Attach two mounting brackets to the front of the frame using three
1/4-20
1
I
hex-head bolts and nuts for each bracket. The front of
the frame is the end with metal tabs.
Attach two mounting brackets to the rear of the frame using two
10-32
1/2
I
hex-head bolts and flat washers for each bracket.
Tabs
Frame Front
Figure 6. Frame Assembly
3.
To ensure the front panel bolts align with the holes in the rack, use
the slot measurements in Figure 7 to position the frame before you
attach it to the rack.
19.0
I
(48.3 cm)
1.5
I
(3.8 cm)
4.0
I
(10.2 cm)
3.0
I
(7.6 cm)
4.0
I
(10.2 cm)
1.5
I
(3.8 cm)
14.0
I
(35.6 cm)
Figure 7. RBC-1 and RBC-2 Front Panel Bolt Slot Measurements