24
GREEN MOTION DC 44/66 EV CHARGER INSTALLATION MANUAL
MN192006EN March 2023 www.eaton.com
00 Title
7.1 Unit switch-on
Before switching on the EV charger, check the effectiveness of the safety measure(s) of the system in
accordance with the local regulations.
Electrical systems or devices must be checked by the installer of the system before commissioning and
switching on the unit.
Before switching on the product, please do the following:
Step 1.
Check that the equipment is correctly fixed on the concrete base in accordance with local
regulations.
Step 2.
Check that the electrical connections have been made correctly in accordance with local regulations.
Step 3.
Check that the EARTH connection (MANDATORY) has been made correctly in accordance with local
regulations.
Step 4.
Perform checks on the continuity of the connections of the protective conductor, insulation
resistance, RCD triggering current, triggering time, etc., in accordance with local regulations.
Step 5.
Verify that the front door is closed and secured with the cam locks.
If the checks listed above were successful, proceed as follows:
Step 1.
Close the main AC GRID circuit breakers.
Step 2.
Wait for the display to turn on.
Step 3.
Visit the link or scan the QR code to fill out the installation checklist form at:
https://content.eaton.com/en-gb-installation-checklist-ev-chargers
Figure 16. QR code for the installation checklist online form