15
XCHARGEIN MOBILITY INSTALLATION MANUAL
MN191005EN April 2021 www.eaton.com
00
Title
5.2.2 Mounting on the column (optional)
Fix the column with 4 x M8 stainless steel threaded rods on a 350 mm x 350 mm (minimum) concrete base.
The power input electrical cable is fed through the center. The power input cable should have a 135 cm service loop
length (length measurement from the floor).
Below is a schematic representation of the base of the charging station column to be mounted on the floor.
Figure 9. The base of the charging station column with dimensions in mm
310 mm
8 x Ø15 mm
204 mm
150 mm
270 mm
80 mm
31
0 mm
270 mm
125 mm
130 mm
50 mm
Ø15 mm
The charging station should be fixed on the column with M6 stainless steel screws.
Once done, the cable cover should be installed on the column with M3 stainless steel screws.
There are two cable cover models:
1. Cable cover to protect the cables under the charging station.
2. Cable top to be installed on the top of the column in the absence of the second charging station.
Figure 10. Detail of cable covers for stand mounting