32
XCHARGEIN MOBILITY INSTALLATION MANUAL
MN191005EN April 2021 www.eaton.com
00 Title
Register
Address
Always or
optional
R/W
Description
40015
14
Optional
R
Energy consumption:
In Wh (unsigned integer 32 bit)
40016
15
40017
16
Optional
W
Set energy consumption:
In Wh (unsigned integer 32 bit): if 0,
reset the energy consumption. If other value, the written value should
be added to current value (used when the charger does not have a
persistent energy consumption mechanism).
40018
17
40019
18
Optional
R
Instant energy consumption:
In W
40020
19
40021
20
Optional
R
Instant current consumption:
In A
40022
21
Optional
R
Plug type:
0 = None
1 = Socket_Mode 1
2 = Socket_Mode_3_Type2
3 = Plug_Mode3_Type1
4 = Plug_Mode3_Type2
40023
22
Optional
R
Current type:
0 = AC
1 = DC
40024
23
Optional
R
Phase count:
0 = DC charger
1 = Single-phase charger
3 = Three-phase charger
40025
24
Optional
R/W
RFID serial status:
0 = Serial number has been already processed
1 = A new RFID serial number is available
40026
25
Optional
R
RFID serial number:
(Unsigned integer 64 bit)
25 = LSB
28 = MSB
40027
26
40028
27
40029
28
7.3 Unit switch-on
Before switching on the station, check the effectiveness of the safety measure(s) of the system in
accordance with the local regulations.
Electrical systems or devices must be checked by the installer of the system before commissioning and
switching on the unit.
Before switching on the product, please do the following:
1. Check that the equipment is correctly fixed to the wall or the floor stand in accordance with local regulations.
2. Check that the AC GRID connections have been made correctly in accordance with local regulations.
3. Check that the EARTH connection (MANDATORY) has been made correctly in accordance with local
regulations.
4. Perform checks on the continuity of the connections of the protective conductor, insulation resistance,
RCD triggering current, triggering time, etc., in accordance with local regulations.
5. Verify that the connection cover is closed and secured with the fixing screws.
If the checks listed above were successful, proceed as follows:
1. Turn on to establish grid connection.
2. Turn on the main AC GRID circuit breakers.
3. Wait for the display to turn on.