Installing Battery Cabinets
3-11
EATON
Powerware
®
9390 Integrated Battery Cabinet (Models IBC-S and IBC-L) Installation Manual
S
164201536 Rev D
www.eaton.com/powerquality
6.
Remove the cosmetic cover and hanger brackets from the appropriate side or
sides of the battery cabinets, depending on the position of the cabinets. Save
covers, screws, and brackets for later use.
7.
Roll the next battery cabinet to be joined to an area near the appropriate side of
the first battery cabinet.
8.
Push the battery cabinet to be joined towards the first battery cabinet until the
doors are flush with each other.
9.
Secure the battery cabinet position by lowering the leveling feet until cabinet is
not resting on the casters. Ensure the cabinet is level and matches the height of
the first installed battery cabinet.
NOTE
Two cabinet joining brackets are provided in the field kit for securing each
cabinet at the top and bottom. A small flat bracket joins the top of the cabinets, and a
larger angle bracket joins the cabinets at the bottom. The flat bracket is attached to the
cabinet tops first.
10.
Locate the small flat bracket from the field kit. Align the holes in the flat bracket
over the two holes in the top front of the cabinets. Secure the bracket to the
cabinets with screws from the field kit (see Figure 3‐3).
11.
Locate the large angle bracket from the field kit. Place one end of the bracket
over the bolt on the bottom side of the lower left‐hand hinge on the adjacent
battery cabinet, and secure the bracket to the hinge with hardware from the field
kit (see Figure 3‐4).
12.
Align the holes in the other end of the bracket with the holes in the bottom
right-hand side of the next battery cabinet (see Figure 3‐4). Secure the bracket
with hardware from the field kit.
13.
Route the ground wire (from the field kit) from the ground stud in one battery
cabinet, under the lower battery tray and through the cabinet-to-cabinet cable
access area in the side of the cabinets, and attach to the ground stud in the other
battery cabinet (see Figure 3‐4 and Figure 3‐5). Hardware is provided on each
ground stud.
14.
If installing additional battery cabinets, repeat Steps 6 through 13 to join each
additional battery cabinet; otherwise, proceed to Step 15.
15.
If not already installed, mount the hanger brackets to the top appropriate side of
the last battery cabinet using M4 screws (see Figure 3‐5).
16.
If not already installed, hang the side panel on the hanger brackets and align with
the front and rear of the battery cabinet.
17.
If not already secured, secure the side panel at the bottom using M4 hex-head
screws previously removed.
18.