Eaton 93PM Integrated Battery Cabinet-Small Welded (IBC-SW) Installation Manual 164000639—Rev 03
37
2.
Line-Up-and-Match Wiring.
Route the battery detect interface wiring from the UPS battery detect
interface terminals through the top inter-cabinet access pass-through (see
) of the UPS cabinet and
IBC–SW to the IBC–SW battery interface terminal block TB2. See
for terminal locations. See
paragraph
IBC–SW Interface Wiring Preparation
,
, and
for wiring and termination
requirements. Refer to the applicable Eaton 93PM UPS Installation and Operation manual listed in
paragraph
, for UPS cabinet terminal locations.
3.
Proceed to
Step 10
.
4.
Top Entry Wiring.
Remove the top conduit plate (see
) from the top of the IBC–SW. Identify all
conduit requirements and mark their location. Drill and punch all conduit holes in the top conduit plate prior
to mounting on the IBC–SW. Install the conduit plate and install all conduit runs into the plate. Pull the
wiring through the conduit into the wiring area.
NOTE
In multiple IBC–SW installations, route the battery interface wiring between IBC–SWs
through the top of the adjacent IBC–SW using the top side inter-cabinet access pass-
through (see
5.
Route the battery detect interface wiring from the UPS battery detect interface terminals through top of
the IBC–SW to the IBC–SW battery interface terminal block TB2. See
for terminal locations. See
paragraph
IBC–SW Interface Wiring Preparation
,
, and
for wiring and termination
requirements. Refer to the applicable Eaton 93PM UPS Installation and Operation manual listed in
paragraph
, for UPS cabinet terminal locations.
6.
Proceed to
Step 10
.
7.
Bottom Entry Wiring.
Remove the bottom conduit plate (see
) from the inside bottom of the
IBC–SW. Identify all conduit requirements and mark their location. Drill and punch all conduit holes in the
bottom conduit plate prior to mounting on the IBC–SW. Install the conduit plate and install all conduit runs
into the plate. Pull the wiring through the conduit into the wiring areas.
NOTE
In multiple IBC–SW installations, route the battery interface wiring between IBC–SWs
through the top of the adjacent IBC–SW using the top side inter-cabinet access pass-
through (see
8.
Route the battery detect interface wiring from the UPS battery detect interface terminals through the
bottom of the IBC–SW to the wiring channel on the left side of the IBC–SW (see
). Route the
wiring along the wiring channel to the IBC–SW battery interface terminal block TB2. See
for
terminal locations. See paragraph
IBC–SW Interface Wiring Preparation
,
, and
for
wiring and termination requirements. Refer to the applicable Eaton 93PM UPS Installation and Operation
manual listed in paragraph
, for UPS cabinet terminal locations.
9.
Secure the interface wiring to the wire tie anchors (see
) using Zip ties.
10. Connect the battery detect interface wiring to the IBC–SW battery detect interface terminals. See
paragraph
IBC–SW Interface Wiring Preparation
and
for termination requirements.
For a detailed view of the IBC–SW terminal block, see
.
11. Connect the battery detect interface wiring to the UPS battery detect interface terminals. Refer to the
applicable Eaton 93PM UPS Installation and Operation manual listed in paragraph
, for UPS cabinet termination requirements.
NOTE
In the following step, if the safety shield cannot be reinstalled because of misalignment,
use the leveling feet to realign the cabinet.
12. Reinstall the internal safety shield panel removed in
Step 3
of paragraph
Line-Up-and-Match Power Wiring
.