36
Eaton 93PM Integrated Battery Cabinet-Small Welded (IBC-SW) Installation Manual 164000639—Rev 03
Figure 16. Top and Bottom Entry Conduit and Wire Entry Locations
Access plate for
Service use only.
**Not to be used for
conduit routing**
Top Entry Conduit
Landing for DC Output /
Interface wiring
(Remove panel to drill
or punch conduit holes.)
Bottom Entry Conduit
Landing for DC Output /
Interface wiring
(Remove panel to drill
or punch conduit holes.)
Top
View
Bottom
View
Front
Front
44..44
IInnssttaalllliinngg IIB
BC
C––S
SW
W IInntteerrffaaccee W
Wiirriinngg
IBC–SWs can be installed in a line-up-and-match configuration with the interface wiring routed through the
IBC–SWs and UPS cabinet or in a standalone configuration with the interface wiring routed between the IBC–
SWs and the UPS cabinet using conduit.
44..44..11
IInnssttaalllliinngg B
Baatttteerryy D
Deetteecctt IInntteerrffaaccee C
Coonnnneeccttiioonnss
NOTE 1
Disconnect terminal block plug from terminal block to wire plug.
NOTE 2
If the inter-cabinet wiring access pass-through is not used to install the battery detect
interface wiring connections, conduit must be installed between the battery cabinet and
the UPS cabinet.
To install wiring:
1.
If wiring the IBC–SW battery detect interface terminals using line-up-and-match wiring using the inter-
cabinet wiring access pass-through (see
) continue to
Step 2
; if wiring the IBC–SW battery detect
interface terminals using the top entry access, proceed to
Step 5
; if wiring the IBC–SW battery detect
interface terminals using the bottom entry access, proceed to
Step 8
.
NOTE
In multiple IBC–SW installations, route the battery interface wiring between IBC–SWs
through the top of the adjacent IBC–SW using the top side inter-cabinet access pass-
through (see
).
Summary of Contents for IBC-SW