53
User Manual
MN013016EN
Effective July 2022
Magnum PXR and Power Defense SB low
voltage power circuit breakers user manual
EATON
www.eaton.com
Figure 91. Levering-in door in position between disconnect
and test
There are NO impediments to tripping/opening . The circuit breaker will
always be permitted to open on command of the following:
•
OPEN pushbutton is depressed
•
Shunt trip (electrical)
•
External trip interlock (cassette)
•
UVR being de-energized (electrical)
•
Trip unit signal (overcurrent etc .)
•
Rotating the interlock wire form
•
For breakers used in multi-way interlocks with other breakers,
testing should be performed as described in the appropriate
instruction manual
ote:
N
Drawout breakers must be installed in their cassette . To verify proper
operation of multi-way interlocks, the breaker will be required to close and
open while installed in the switchgear .